The town's engineers found unfinished punch-list work on the Alinga Construction project, so the board paid only 80% of the invoice and is holding the rest until the work is done.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 15, 2026.
Impact analysis
The town is paying $23,960 now and holding back $5,990 of the $29,950 billed.
Town taxpayers are protected from paying in full for work that isn't finished yet.